No, please do not assume it. Ninety to one hundred and eighty days is a reasonable planning estimate for many states. My own published rate sheet uses that range for a number of states, including Wyoming, Delaware and Mississippi. But it is an estimate, not a promise, and a lot depends on the applicant.
Please understand what any timeframe actually measures. There are really three separate periods:
- Preparation. Before anything is filed, the business, the documents and the NMLS records have to be ready. For a first application, this often takes three to four months, sometimes longer if documents have to be built from scratch or foreign records have to be obtained.
- Initial review and completeness. After submission, the regulator checks whether the application is complete. If it is not, the clock you care about may not have really started yet.
- Substantive review and decision. Once the application is complete, the regulator reviews it in detail, asks questions and makes a decision.
Some statutes set a review period, but they usually count from a complete application, not from your first filing. Wyoming's statute, for example, requires a decision on an original licence within 120 days of a complete application, unless extended with the applicant's consent. That is useful, but it does not help you if the application sits incomplete for weeks while you gather documents.
Across the country, individual state reviews can take anywhere from about three months to twelve months, and the larger states like New York, California and Texas commonly take much longer. Broad multi-state coverage commonly takes 18 to 24 months or more.
The things that most affect timing are within your control:
- Completeness and consistency of the application.
- How quickly your team answers regulator questions.
- Clean, verifiable ownership and source of funds.
- Ready background checks, especially for owners who have lived abroad.
- Financial statements in the form the state requires.
Please also do not confuse a support period with an approval deadline. In my standalone service, support runs 60 days from submission. That is how long the adviser supports you, not how long the regulator will take. If the review is likely to run longer, plan for an extension or a package.
And, of course, no consultant or applicant can guarantee the application result or the timing. What we can do is make sure the application is complete and strong, which is the best way to keep the review short.